From: Bill Verzal (BVerzal@KOMATSUNA.COM)
Date: Thu Mar 11 2004 - 14:19:36 EST
HACMP cannot be upgraded in this way AFAIK.
BV
--------------------------------------------------------
"If everything is coming your way, then you are in the wrong lane"
Bill Verzal
AIX Administrator, Komatsu America
(847) 970-3726 - direct
(847) 970-4184 - fax
Robert Miller
<rmiller@SMUD.ORG
> To
Sent by: IBM AIX aix-l@Princeton.EDU
Discussion List cc
<aix-l@Princeton.
EDU> Subject
HACMP upgrades
03/11/2004 12:59
PM
Please respond to
IBM AIX
Discussion List
<aix-l@Princeton.
EDU>
Folks,
We're looking at moving some B80's from AIX 4.3.3 to 5.2, and upgrading
HACMP from v4.3 to v5.1.
The setup is running Oracle Parallel Server, with one box able to write to
the SSA-attached drives at a time.
The question is this: is it possible to shut down one box, upgrade AIX and
HACMP, then shut down the databases and the other box, bring the databases
up on the upgraded box, and then update the other machine?
I'm wondering what kind of "gotcha's" there are, if any, that I'll need to
look at or figure out...
Thanks!
--rm
This archive was generated by hypermail 2.1.7 : Wed Apr 09 2008 - 22:17:41 EDT